Question

Case Study

Case Study 2:Southwestern University (pp. 94–95). Complete the Case Studies assignment listed below. The Case Study grading rubric is posted in Doc Sharing—refer to the Case Studies Assignment Rubric document..

• Complete the three questions at the end of the case on page 95.

Submit your assignment to the Dropbox, located at the top of this page. For instructions on how to use the Dropbox, read these step-by-step instructions.

See the Syllabus section "Due Dates for Assignments & Exams" for due date information.

    1. Develop a network drawing for Hill Construction and determine the critical path. How long is the project expected to take?

    2. What is the probability of finishing in 270 days?

    3. If it is necessary to crash to 250 or 240 days, how would Hill do so, and at what costs? As noted in the case, assume that optimistic time estimates can be used as crash times.

 

Top Reviews
EYS***751 2019-09-18 11:04:51
Slight grammar mistakes, but content is accurate.

Solution Preview

240 days would cost $34,000

250 days would cost $15,000

He would crash the two most inexpensive at crash costs per day, being task A & D. This would be the cheapest option as well as most 